Feckenham 400kV Substation

Feckenham 400kV Substation (NGET) has 8 projects in NESO's TEC Register of 23 Oct 2026: 3,375 MW in the queue, 1,350 MW Gate 1, and 29 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
8
MW in the queue
3,375 MW
Gate 1 MW
1,350 MW
MW connected
29 MW

By technology

TechnologyProjectsMW
Storage73,375
Solar52,725
Demand21,425
Gas129

Projects at Feckenham 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
Feckenham Green Energy CentreDemand, Storage, Solar1,025Scoping30 Oct 2032
FeckenhamStorage, Solar500Scoping21 Jul 2029
Feckenham Energy ParkStorage500Scoping31 Oct 2033
Boom Power Feckenham Generation HubStorage, Solar400Gate 1Scoping31 Oct 2033
FeckenhamDemand, Storage, Solar400Gate 1Awaiting Consents31 Oct 2036
Feckenham PV & BESS StationStorage, Solar400Gate 1Scoping30 Oct 2037
Feckenham Greener Grid ParkStorage12–150Gate 1Scoping31 Oct 2028, 31 Oct 2032
RedditchGas29Built