Fearna Pump Storage Hydro 2 400/15kV Substation (SHET) has 1 project in NESO's TEC Register of 23 Oct 2026: 1,495 MW in the queue, and 0 MW connected. Contracted capacity, not headroom.
Transmission owner
SHET
Projects
1
MW in the queue
1,495 MW
MW connected
0 MW
By technology
Technology
Projects
MW
Pumped storage
1
1,495
Projects at Fearna Pump Storage Hydro 2 400/15kV Substation