Fasnakyle GSP
Fasnakyle GSP (SHET) has 2 projects in NESO's TEC Register of 23 Oct 2026: 0 MW in the queue, and 76.5 MW connected. Contracted capacity, not headroom.
- Transmission owner
- SHET
- Projects
- 2
- MW in the queue
- 0 MW
- MW connected
- 76.5 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Hydro | 2 | 76.5 |
Projects at Fasnakyle GSP
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Fasnakyle G1 & G2 | Hydro | 46 | Built | ||
| Fasnakyle G3 & G4 | Hydro | 30.5 | Built |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.