Grid GuardianOpen this site in the app

Fairburn Extension 132/33kV Substation

Fairburn Extension 132/33kV Substation (SHET) has 1 project in NESO's TEC Register of 23 Oct 2026: 90 MW in the queue, 90 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SHET
Projects
1
MW in the queue
90 MW
Gate 1 MW
90 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Onshore wind190

Projects at Fairburn Extension 132/33kV Substation

ProjectTechnologyMWGateStatusMW effective from
Fairburn Extension Wind FarmOnshore wind90Gate 1Scoping31 Oct 2031

Source