ERBYSHIRE CONNECTION NODE E 132kV SUBSTATION

ERBYSHIRE CONNECTION NODE E 132kV SUBSTATION (NGET) has 1 project in NESO's TEC Register of 23 Oct 2026: 240 MW in the queue, 240 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
1
MW in the queue
240 MW
Gate 1 MW
240 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage1240

Projects at ERBYSHIRE CONNECTION NODE E 132kV SUBSTATION

ProjectTechnologyMWGateStatusMW effective from
Drakelow Power Station 3 BESSStorage240Gate 1Scoping30 Oct 2037