ELVANFOOT ENERGY STORAGE 132/33KV COLLECTOR SUBSTATION

ELVANFOOT ENERGY STORAGE 132/33KV COLLECTOR SUBSTATION (SPT) has 2 projects in NESO's TEC Register of 23 Oct 2026: 75 MW in the queue, 75 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SPT
Projects
2
MW in the queue
75 MW
Gate 1 MW
75 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage275

Projects at ELVANFOOT ENERGY STORAGE 132/33KV COLLECTOR SUBSTATION

ProjectTechnologyMWGateStatusMW effective from
Elvanfoot (50MW) Energy StorageStorage50Gate 1Scoping26 Oct 2029
Elvanfoot (25MW) Energy StorageStorage25Gate 1Scoping26 Oct 2029