Eaton Socon 400kV Substation
Eaton Socon 400kV Substation (NGET) has 4 projects in NESO's TEC Register of 23 Oct 2026: 1,550 MW in the queue, and 740 MW connected. Contracted capacity, not headroom.
- Transmission owner
- NGET
- Projects
- 4
- MW in the queue
- 1,550 MW
- MW connected
- 740 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Storage | 4 | 2,290 |
| Solar | 3 | 1,550 |
| Nuclear | 1 | 1,000 |
| Onshore wind | 1 | 1,000 |
| Reactive Compensation | 1 | 1,000 |
| Gas | 1 | 740 |
Projects at Eaton Socon 400kV Substation
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Eaton Socon High Impact Green Energy Hub (HIGEH) 1 | Storage, Nuclear, Solar, Reactive Compensation, Onshore wind | 1,000 | Scoping | 30 Oct 2033 | |
| Little Barford | Gas, Storage | 740 | Built | ||
| Eaton Socon Solar | Storage, Solar | 500 | Scoping | 31 Oct 2028 | |
| Eaton Socon PV Storage | Storage, Solar | 49.9 | Scoping | 30 Oct 2029 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.