DUNACH WIND 132KV SUBSTATION

DUNACH WIND 132KV SUBSTATION (SHET) has 1 project in NESO's TEC Register of 23 Oct 2026: 100.8 MW in the queue, 100.8 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SHET
Projects
1
MW in the queue
100.8 MW
Gate 1 MW
100.8 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Onshore wind1100.8

Projects at DUNACH WIND 132KV SUBSTATION

ProjectTechnologyMWGateStatusMW effective from
Dunach Wind FarmOnshore wind100.8Gate 1Scoping31 Oct 2034