Dumfries North 400/132kV substation

Dumfries North 400/132kV substation (Mixed) has 2 projects in NESO's TEC Register of 23 Oct 2026: 243.2 MW in the queue, 243.2 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET, SPT
Projects
2
MW in the queue
243.2 MW
Gate 1 MW
243.2 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage2243.2
Solar1200
Onshore wind143.2

Projects at Dumfries North 400/132kV substation

ProjectTechnologyMWGateStatusMW effective from
KellheadStorage, Solar200Gate 1Scoping31 Oct 2037
Balgray Wind FarmStorage, Onshore wind43.2Gate 1Scoping31 Oct 2037