DRUM OF CLUNAS WIND 275KV SUBSTATION
DRUM OF CLUNAS WIND 275KV SUBSTATION (SHET) has 1 project in NESO's TEC Register of 23 Oct 2026: 150 MW in the queue, 150 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.
- Transmission owner
- SHET
- Projects
- 1
- MW in the queue
- 150 MW
- Gate 1 MW
- 150 MW
- MW connected
- 0 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Onshore wind | 1 | 150 |
Projects at DRUM OF CLUNAS WIND 275KV SUBSTATION
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Drum of Clunas Wind and Solar Park | Onshore wind | 150 | Gate 1 | Scoping | 31 Oct 2031 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.