Drakelow 400kV Substation

Drakelow 400kV Substation (NGET) has 10 projects in NESO's TEC Register of 23 Oct 2026: 3,366 MW in the queue, 252.3 MW of it Gate 2, 1,009 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
10
MW in the queue
3,366 MW
Gate 2 MW
252.3 MW
Gate 1 MW
1,009 MW
MW connected
0 MW
Earliest confirmed date
30 Jun 2027

By technology

TechnologyProjectsMW
Storage92,986
Solar52,327
Demand11,025
Gas1380

Projects at Drakelow 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
Drakelow Green Energy CentreDemand, Storage, Solar400–1,025Awaiting Consents30 Apr 2028, 30 Oct 2029
Greta IIIStorage, Solar500Consents Approved30 Oct 2029
Drakelow PV & BESS StationStorage, Solar400Gate 1Scoping30 Oct 2037
Powersite @ DrakelowGas380Under Construction/Commissioning1 Oct 2020
Caldwell RoadStorage249Gate 1Scoping30 Oct 2028
Walton Road Energy ProjectStorage, Solar240Gate 1Scoping31 Oct 2029
Drakelow BESSStorage200Consents Approved31 Dec 2029
Oaklands Farm Solar PVStorage, Solar162.3Gate 2Consents Approved30 Jun 2027
DrakelowStorage120Gate 1Scoping1 Dec 2027
Royle Farm BESSStorage90Gate 2Consents Approved31 Oct 2028

Source