Dorenell 132/33kV Substation

Dorenell 132/33kV Substation (SHET) has 1 project in NESO's TEC Register of 23 Oct 2026: 0 MW in the queue, and 177 MW connected. Contracted capacity, not headroom.

Transmission owner
SHET
Projects
1
MW in the queue
0 MW
MW connected
177 MW

By technology

TechnologyProjectsMW
Onshore wind1177

Projects at Dorenell 132/33kV Substation

ProjectTechnologyMWGateStatusMW effective from
Dorenell WindfarmOnshore wind177Built