Dersalloch 132/33kV
Dersalloch 132/33kV (SPT) has 2 projects in NESO's TEC Register of 23 Oct 2026: 11 MW in the queue, and 69 MW connected. Contracted capacity, not headroom.
- Transmission owner
- SPT
- Projects
- 2
- MW in the queue
- 11 MW
- MW connected
- 69 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Onshore wind | 1 | 69 |
| Storage | 1 | 11 |
Projects at Dersalloch 132/33kV
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Dersalloch Wind Farm | Onshore wind | 69 | Built | ||
| Dersalloch Wind Farm Extension | Storage | 11 | Scoping | 31 Oct 2027 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.