Derbyshire Connection Node F 132KV

Derbyshire Connection Node F 132KV (NGET) has 2 projects in NESO's TEC Register of 23 Oct 2026: 350 MW in the queue, 350 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
2
MW in the queue
350 MW
Gate 1 MW
350 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage2350
Solar1200

Projects at Derbyshire Connection Node F 132KV

ProjectTechnologyMWGateStatusMW effective from
Ratcliffe on SoarStorage, Solar200Gate 1Scoping31 Oct 2037
Prestwold BESSStorage150Gate 1Scoping30 Oct 2037