Grid GuardianOpen this site in the app

Derbyshire Connection Node C 400kV Substation

Derbyshire Connection Node C 400kV Substation (NGET) has 1 project in NESO's TEC Register of 23 Oct 2026: 1,000 MW in the queue, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
1
MW in the queue
1,000 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Demand11,000
Solar11,000
Storage11,000

Projects at Derbyshire Connection Node C 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
Ratcliffe on Soar FarmDemand, Storage, Solar1,000Scoping30 Oct 2033

Source