Cumberhead Collector 132/33kV

Cumberhead Collector 132/33kV (SPT) has 1 project in NESO's TEC Register of 23 Oct 2026: 0 MW in the queue, and 42 MW connected. Contracted capacity, not headroom.

Transmission owner
SPT
Projects
1
MW in the queue
0 MW
MW connected
42 MW

By technology

TechnologyProjectsMW
Onshore wind142

Projects at Cumberhead Collector 132/33kV

ProjectTechnologyMWGateStatusMW effective from
Dalquhandy Wind FarmOnshore wind42Built