Cruachan 275kV Substation

Cruachan 275kV Substation (SPT) has 2 projects in NESO's TEC Register of 23 Oct 2026: 600 MW in the queue, 480 MW of it Gate 2, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SPT
Projects
2
MW in the queue
600 MW
Gate 2 MW
480 MW
MW connected
0 MW
Earliest confirmed date
4 Apr 2029

By technology

TechnologyProjectsMW
Pumped storage21,080

Projects at Cruachan 275kV Substation

ProjectTechnologyMWGateStatusMW effective from
Cruachan ExpansionPumped storage600Scoping31 Oct 2030
Cruachan U3&4 ReplacementPumped storage440–480Gate 2Built, Consents Approved4 Apr 2029

Source