CRAIG WATCH WIND FARM 132KV SUBSTATION

CRAIG WATCH WIND FARM 132KV SUBSTATION (SHET) has 1 project in NESO's TEC Register of 23 Oct 2026: 72.6 MW in the queue, 72.6 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SHET
Projects
1
MW in the queue
72.6 MW
Gate 1 MW
72.6 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Onshore wind172.6

Projects at CRAIG WATCH WIND FARM 132KV SUBSTATION

ProjectTechnologyMWGateStatusMW effective from
Craig Watch Wind FarmOnshore wind72.6Gate 1Awaiting Consents15 May 2031