Grid GuardianOpen this site in the app

Coventry 275kV Substation

Coventry 275kV Substation (NGET) has 2 projects in NESO's TEC Register of 23 Oct 2026: 0 MW in the queue, and 55.9 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
2
MW in the queue
0 MW
MW connected
55.9 MW

By technology

TechnologyProjectsMW
Solar149.9
Storage149.9
Oil & AGT (Advanced Gas Turbine)16

Projects at Coventry 275kV Substation

ProjectTechnologyMWGateStatusMW effective from
CoventryStorage, Solar49.9Built
PeakGen BEGA - CoventryOil & AGT (Advanced Gas Turbine)6Built

Source