Coryton South 400kV Substation
Coryton South 400kV Substation (NGET) has 2 projects in NESO's TEC Register of 23 Oct 2026: 1,000 MW in the queue, and 850 MW connected. Contracted capacity, not headroom.
- Transmission owner
- NGET
- Projects
- 2
- MW in the queue
- 1,000 MW
- MW connected
- 850 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Storage | 1 | 1,000 |
| Gas | 1 | 850 |
Projects at Coryton South 400kV Substation
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Gateway Energy Centre Power Station | Storage | 450–1,000 | Consents Approved | 30 Jun 2029, 30 Oct 2029 | |
| Coryton | Gas | 850 | Built | 30 Oct 2029 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.