Corriegarth 132/33kV substation
Corriegarth 132/33kV substation (SHET) has 2 projects in NESO's TEC Register of 23 Oct 2026: 70 MW in the queue, and 69 MW connected. Contracted capacity, not headroom.
- Transmission owner
- SHET
- Projects
- 2
- MW in the queue
- 70 MW
- MW connected
- 69 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Onshore wind | 2 | 139 |
Projects at Corriegarth 132/33kV substation
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Corriegarth 2 Wind Farm | Onshore wind | 70 | Scoping | 31 Jul 2027 | |
| Corriegarth | Onshore wind | 69 | Built |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.