Corriegarth 132/33kV substation

Corriegarth 132/33kV substation (SHET) has 2 projects in NESO's TEC Register of 23 Oct 2026: 70 MW in the queue, and 69 MW connected. Contracted capacity, not headroom.

Transmission owner
SHET
Projects
2
MW in the queue
70 MW
MW connected
69 MW

By technology

TechnologyProjectsMW
Onshore wind2139

Projects at Corriegarth 132/33kV substation

ProjectTechnologyMWGateStatusMW effective from
Corriegarth 2 Wind FarmOnshore wind70Scoping31 Jul 2027
CorriegarthOnshore wind69Built