Corby 132kV Substation

Corby 132kV Substation (NGET) has 1 project in NESO's TEC Register of 23 Oct 2026: 0 MW in the queue, and 401 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
1
MW in the queue
0 MW
MW connected
401 MW

By technology

TechnologyProjectsMW
Gas1401

Projects at Corby 132kV Substation

ProjectTechnologyMWGateStatusMW effective from
CorbyGas401Built