Grid GuardianOpen this site in the app

Coille Linne 132kV Substation

Coille Linne 132kV Substation (SHET) has 1 project in NESO's TEC Register of 23 Oct 2026: 113 MW in the queue, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SHET
Projects
1
MW in the queue
113 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Onshore wind1113
Storage1113

Projects at Coille Linne 132kV Substation

ProjectTechnologyMWGateStatusMW effective from
Coille LinneStorage, Onshore wind113Scoping31 Oct 2037

Source