Clauchrie 132/33KV Substation

Clauchrie 132/33KV Substation (SPT) has 1 project in NESO's TEC Register of 23 Oct 2026: 108 MW in the queue, 108 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SPT
Projects
1
MW in the queue
108 MW
Gate 1 MW
108 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Onshore wind1108
Storage1108

Projects at Clauchrie 132/33KV Substation

ProjectTechnologyMWGateStatusMW effective from
Clauchrie WindfarmStorage, Onshore wind108Gate 1Scoping31 May 2033