Chirmorie Wind Farm substation

Chirmorie Wind Farm substation (SPT) has 1 project in NESO's TEC Register of 23 Oct 2026: 91 MW in the queue, 91 MW of it Gate 2, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SPT
Projects
1
MW in the queue
91 MW
Gate 2 MW
91 MW
MW connected
0 MW
Earliest confirmed date
30 Apr 2027

By technology

TechnologyProjectsMW
Onshore wind191

Projects at Chirmorie Wind Farm substation

ProjectTechnologyMWGateStatusMW effective from
Chirmorie Wind FarmOnshore wind91Gate 2Consents Approved30 Apr 2027