Chirk GSP
Chirk GSP (NGET) has 7 projects in NESO's TEC Register of 23 Oct 2026: 943 MW in the queue, 150 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.
- Transmission owner
- NGET
- Projects
- 7
- MW in the queue
- 943 MW
- Gate 1 MW
- 150 MW
- MW connected
- 0 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Onshore wind | 7 | 943 |
Projects at Chirk GSP
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Moel y Llyn | Onshore wind | 251 | Scoping | 4 Feb 2027 | |
| Dolyfardyn | Onshore wind | 165 | Scoping | 4 Feb 2027 | |
| Maesnant Energy Park | Onshore wind | 150 | Gate 1 | Scoping | 1 Nov 2033 |
| Llwynygog | Onshore wind | 125 | Scoping | 4 Feb 2027 | |
| Bryn Tilti | Onshore wind | 106 | Scoping | 4 Feb 2027 | |
| Llyn Lort II Energy Park | Onshore wind | 100 | Scoping | 1 Nov 2037 | |
| Blaen y Glyn | Onshore wind | 46 | Scoping | 4 Feb 2027 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.