Chirk GSP

Chirk GSP (NGET) has 7 projects in NESO's TEC Register of 23 Oct 2026: 943 MW in the queue, 150 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
7
MW in the queue
943 MW
Gate 1 MW
150 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Onshore wind7943

Projects at Chirk GSP

ProjectTechnologyMWGateStatusMW effective from
Moel y LlynOnshore wind251Scoping4 Feb 2027
DolyfardynOnshore wind165Scoping4 Feb 2027
Maesnant Energy ParkOnshore wind150Gate 1Scoping1 Nov 2033
LlwynygogOnshore wind125Scoping4 Feb 2027
Bryn TiltiOnshore wind106Scoping4 Feb 2027
Llyn Lort II Energy ParkOnshore wind100Scoping1 Nov 2037
Blaen y GlynOnshore wind46Scoping4 Feb 2027