Chickerell-Mannington 400kV Substation

Chickerell-Mannington 400kV Substation (NGET) has 1 project in NESO's TEC Register of 23 Oct 2026: 43.2 MW in the queue, 43.2 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
1
MW in the queue
43.2 MW
Gate 1 MW
43.2 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Demand143.2
Solar143.2
Storage143.2

Projects at Chickerell-Mannington 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
Frome Valley Energy ParkDemand, Storage, Solar43.2Gate 1Scoping31 Oct 2039