Chickerell B 400kV Substation

Chickerell B 400kV Substation (NGET) has 1 project in NESO's TEC Register of 23 Oct 2026: 480 MW in the queue, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
1
MW in the queue
480 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Solar1480
Storage1480

Projects at Chickerell B 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
Moreton EstateStorage, Solar480Scoping28 Apr 2037