CELTIC SEA 275/66KV OFFSHORE SUBSTATION

CELTIC SEA 275/66KV OFFSHORE SUBSTATION (NGET) has 1 project in NESO's TEC Register of 23 Oct 2026: 1,000 MW in the queue, 1,000 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
1
MW in the queue
1,000 MW
Gate 1 MW
1,000 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Offshore wind11,000

Projects at CELTIC SEA 275/66KV OFFSHORE SUBSTATION

ProjectTechnologyMWGateStatusMW effective from
Celtic Sea Offshore Wind Farm (ESB)Offshore wind1,000Gate 1Scoping31 Oct 2031