Carrick Wind Farm Substation

Carrick Wind Farm Substation (SPT) has 1 project in NESO's TEC Register of 23 Oct 2026: 84 MW in the queue, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SPT
Projects
1
MW in the queue
84 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Onshore wind184

Projects at Carrick Wind Farm Substation

ProjectTechnologyMWGateStatusMW effective from
Carrick Wind FarmOnshore wind84Awaiting Consents1 Apr 2030