CARRADALE 3 132/33KV GRID SUPPLY POINT SUBSTATION

CARRADALE 3 132/33KV GRID SUPPLY POINT SUBSTATION (SHET) has 2 projects in NESO's TEC Register of 23 Oct 2026: 124.8 MW in the queue, 124.8 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SHET
Projects
2
MW in the queue
124.8 MW
Gate 1 MW
124.8 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Onshore wind2124.8

Projects at CARRADALE 3 132/33KV GRID SUPPLY POINT SUBSTATION

ProjectTechnologyMWGateStatusMW effective from
Allt Domhain Wind FarmOnshore wind64.8Gate 1Scoping31 Oct 2035
Killean Wind FarmOnshore wind60Gate 1Scoping31 Oct 2034