Carradale 2 132/33kV GSP Substation

Carradale 2 132/33kV GSP Substation (SHET) has 1 project in NESO's TEC Register of 23 Oct 2026: 50 MW in the queue, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SHET
Projects
1
MW in the queue
50 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Onshore wind150

Projects at Carradale 2 132/33kV GSP Substation

ProjectTechnologyMWGateStatusMW effective from
West TorrisdaleOnshore wind50Scoping31 May 2028