Grid GuardianOpen this site in the app

Camblesforth 66kV Substation

Camblesforth 66kV Substation (NGET) has 1 project in NESO's TEC Register of 23 Oct 2026: 0 MW in the queue, and 32 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
1
MW in the queue
0 MW
MW connected
32 MW

By technology

TechnologyProjectsMW
Onshore wind132

Projects at Camblesforth 66kV Substation

ProjectTechnologyMWGateStatusMW effective from
Goole Fields Wind FarmOnshore wind32Built

Source