Cairnford GSP
Cairnford GSP (SHET) has 3 projects in NESO's TEC Register of 23 Oct 2026: 145.8 MW in the queue, 63 MW of it Gate 2, 43.2 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.
- Transmission owner
- SHET
- Projects
- 3
- MW in the queue
- 145.8 MW
- Gate 2 MW
- 63 MW
- Gate 1 MW
- 43.2 MW
- MW connected
- 0 MW
- Earliest confirmed date
- 4 Jun 2027
By technology
| Technology | Projects | MW |
|---|---|---|
| Onshore wind | 3 | 145.8 |
| Storage | 1 | 43.2 |
Projects at Cairnford GSP
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Clashindarroch 2 | Onshore wind | 63 | Gate 2 | Under Construction/Commissioning | 4 Jun 2027 |
| Cairnborrow Wind Energy Hub | Storage, Onshore wind | 43.2 | Gate 1 | Scoping | 31 Oct 2031 |
| Tarbuckle Hill Wind Farm | Onshore wind | 39.6 | Scoping | 31 Oct 2031 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.