BRORA 132/33KV GRID SUPPLY POINT SUBSTATION

BRORA 132/33KV GRID SUPPLY POINT SUBSTATION (SHET) has 2 projects in NESO's TEC Register of 23 Oct 2026: 110 MW in the queue, 110 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SHET
Projects
2
MW in the queue
110 MW
Gate 1 MW
110 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage2110
Onshore wind160

Projects at BRORA 132/33KV GRID SUPPLY POINT SUBSTATION

ProjectTechnologyMWGateStatusMW effective from
Crakaig Wind Energy HubStorage, Onshore wind60Gate 1Scoping31 Oct 2034
AULTCRAGGIE BESSStorage50Gate 1Scoping31 Oct 2034

Source