Branxton 400kV Substation
Branxton 400kV Substation (SPT) has 5 projects in NESO's TEC Register of 23 Oct 2026: 4,677 MW in the queue, 1,000 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.
- Transmission owner
- SPT
- Projects
- 5
- MW in the queue
- 4,677 MW
- Gate 1 MW
- 1,000 MW
- MW connected
- 0 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Offshore wind | 2 | 2,760 |
| Storage | 3 | 1,917 |
| Solar | 1 | 166.61 |
Projects at Branxton 400kV Substation
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Berwick Bank Offshore Wind Farm A | Offshore wind | 1,150–1,380 | Scoping | 31 Oct 2028, 31 Oct 2029 | |
| Berwick Bank Offshore Wind Farm B | Offshore wind | 1,150–1,380 | Scoping | 31 Oct 2029, 30 Jun 2031 | |
| Branxton PV & BESS Station | Storage | 1,000 | Gate 1 | Scoping | 31 Oct 2028 |
| Branxton Energy Storage Facility | Storage | 750 | Scoping | 13 May 2029 | |
| Springfield Solar and Battery | Storage, Solar | 166.61 | Scoping | 31 Oct 2031 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.