Braehead Park 132/33kV

Braehead Park 132/33kV (SPT) has 2 projects in NESO's TEC Register of 23 Oct 2026: 99.9 MW in the queue, 50 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SPT
Projects
2
MW in the queue
99.9 MW
Gate 1 MW
50 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage299.9

Projects at Braehead Park 132/33kV

ProjectTechnologyMWGateStatusMW effective from
Scottish Water Laigh Park STWStorage50Gate 1Scoping28 Jun 2028
Wright Street BESSStorage49.9Scoping31 Oct 2025