BORDERS SOLAR 132/33KV SUBSTATION

BORDERS SOLAR 132/33KV SUBSTATION (SPT) has 1 project in NESO's TEC Register of 23 Oct 2026: 228 MW in the queue, 228 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SPT
Projects
1
MW in the queue
228 MW
Gate 1 MW
228 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Solar1228
Storage1228

Projects at BORDERS SOLAR 132/33KV SUBSTATION

ProjectTechnologyMWGateStatusMW effective from
Borders SolarStorage, Solar228Gate 1Scoping31 Oct 2036