Bicker Fen 400kV Substation

Bicker Fen 400kV Substation (NGET) has 5 projects in NESO's TEC Register of 23 Oct 2026: 1,354 MW in the queue, 57.09 MW of it Gate 2, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
5
MW in the queue
1,354 MW
Gate 2 MW
57.09 MW
MW connected
0 MW
Earliest confirmed date
31 Oct 2026

By technology

TechnologyProjectsMW
Solar51,354
Storage51,354

Projects at Bicker Fen 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
Bicker Fenn Energy ParkStorage, Solar600Scoping1 Jun 2029
Heckington Fen Solar ParkStorage, Solar400Scoping1 Oct 2028
Temple Oaks Renewable Energy ParkStorage, Solar240Awaiting Consents30 Oct 2033
Bicker Fen 1 SolarStorage, Solar49.99–57.09Gate 2Consents Approved, Scoping31 Oct 2026, 1 Apr 2033
Bicker Fen 2 SolarStorage, Solar50–57Awaiting Consents, Scoping27 Jul 2026, 1 Apr 2033

Source