Grid GuardianOpen this site in the app

Berkswell 275kV Substation

Berkswell 275kV Substation (NGET) has 3 projects in NESO's TEC Register of 23 Oct 2026: 349.4 MW in the queue, 200 MW of it Gate 2, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
3
MW in the queue
349.4 MW
Gate 2 MW
200 MW
MW connected
0 MW
Earliest confirmed date
31 Oct 2027

By technology

TechnologyProjectsMW
Storage3349.4
Solar157

Projects at Berkswell 275kV Substation

ProjectTechnologyMWGateStatusMW effective from
Berkswell Energy StorageStorage200Gate 2Under Construction/Commissioning31 Oct 2027
012 NEP Coventry WestStorage92.4Scoping31 Oct 2034
Berkswell (Tertiary)Storage, Solar57Consents Approved30 May 2028

Source