Balnespick Wind Farm 132kV/33kV Substation (SHET) has 1 project in NESO's TEC Register of 23 Oct 2026: 58 MW in the queue, and 0 MW connected. Contracted capacity, not headroom.
Transmission owner
SHET
Projects
1
MW in the queue
58 MW
MW connected
0 MW
By technology
Technology
Projects
MW
Onshore wind
1
58
Storage
1
58