Arecleoch 132/33kV

Arecleoch 132/33kV (SPT) has 2 projects in NESO's TEC Register of 23 Oct 2026: 72.8 MW in the queue, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SPT
Projects
2
MW in the queue
72.8 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Onshore wind2402.8

Projects at Arecleoch 132/33kV

ProjectTechnologyMWGateStatusMW effective from
ArecleochOnshore wind114–330Built, Scoping15 Jun 2032
Arecleoch Extension WindfarmOnshore wind72.8Scoping31 Aug 2026