Grid GuardianOpen this site in the app

Aigas Hydro 132kV Substation

Aigas Hydro 132kV Substation (SHET) has 1 project in NESO's TEC Register of 23 Oct 2026: 0 MW in the queue, and 20 MW connected. Contracted capacity, not headroom.

Transmission owner
SHET
Projects
1
MW in the queue
0 MW
MW connected
20 MW

By technology

TechnologyProjectsMW
Hydro120

Projects at Aigas Hydro 132kV Substation

ProjectTechnologyMWGateStatusMW effective from
Aigas (part of the Beauly Cascade)Hydro20Built

Source