Grid GuardianOpen this site in the app

Achrugan 132kV Substation

Achrugan 132kV Substation (SHET) has 1 project in NESO's TEC Register of 23 Oct 2026: 149 MW in the queue, 149 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SHET
Projects
1
MW in the queue
149 MW
Gate 1 MW
149 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Onshore wind1149
Storage1149

Projects at Achrugan 132kV Substation

ProjectTechnologyMWGateStatusMW effective from
Achrugan Wind FarmStorage, Onshore wind149Gate 1Scoping31 Jul 2030

Source