Grid GuardianOpen this site in the app

132kV bay at Iron Acton Substation

132kV bay at Iron Acton Substation (NGET) has 1 project in NESO's TEC Register of 23 Oct 2026: 0 MW in the queue, 120 MW of it Gate 2, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
1
MW in the queue
0 MW
Gate 2 MW
120 MW
MW connected
0 MW
Earliest confirmed date
30 Sept 2026

By technology

TechnologyProjectsMW
Solar1120
Storage1120

Projects at 132kV bay at Iron Acton Substation

ProjectTechnologyMWGateStatusMW effective from
Iron ActonStorage, Solar99.4–120Gate 2Built, Consents Approved30 Sept 2026