Yaxley BESS

Yaxley BESS is a storage project of 200 MW in NESO's TEC Register of 23 Oct 2026, connecting at North Anglia Connection Node E 400kV Substation (NGET). Status: Scoping.

Customer
Field Yaxley Ltd
Connection site
North Anglia Connection Node E 400kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
200 MW
Agreement
Direct Connection
Status
Scoping
MW effective from
31 Oct 2034
NESO project number
PRO-003964

Also at North Anglia Connection Node E 400kV Substation

ProjectTechnologyMW
Dove SolarStorage, Solar500
EPL SuffolkStorage, Solar480
Lightsource Yaxley PVStorage, Solar240
Noventum YaxleyStorage, Solar150
YaxleyDemand, Storage, Solar, Reactive Compensation520
Zenobe Yaxley BESSStorage300