YAMAL BESS

YAMAL BESS is a storage project of 50 MW in NESO's TEC Register of 23 Oct 2026, connecting at MacDuff 132/33kV GSP Substation (SHET). Status: Scoping. Gate 1.

Customer
OPDE UK LIMITED
Connection site
MacDuff 132/33kV GSP Substation
Transmission owner
SHET
Technology
Storage
Capacity (TEC)
50 MW
Agreement
Embedded
Gate
Gate 1
Status
Scoping
MW effective from
31 Oct 2033
NESO project number
PRO-005918