Grid GuardianOpen the evidence in the app

Wymondley High Impact Green Energy Hub (HIGEH) 1

Wymondley High Impact Green Energy Hub (HIGEH) 1 is a storage, solar, reactive compensation, onshore wind project of 1,000 MW in NESO's TEC Register of 23 Oct 2026, connecting at Wymondley 400kV Substation (NGET). Status: Scoping.

Customer
TELIS ENERGY UK LIMITED
Connection site
Wymondley 400kV Substation
Transmission owner
NGET
Technology
Storage, Solar, Reactive Compensation, Onshore wind
Capacity (TEC)
1,000 MW
Agreement
Direct Connection
Status
Scoping
MW effective from
31 Oct 2033
NESO project number
PRO-002659

Also at Wymondley 400kV Substation

ProjectTechnologyMW
Green Frog @ LetchworthGas15
WymondleyStorage, Solar400
WymondleyStorage, Solar57
Wymondley BESS LimitedStorage35.5
Wymondley Solar FarmStorage, Solar50

Source