Woodbridge - Noventum
Woodbridge - Noventum is a demand, storage, reactive compensation project of 400 MW in NESO's TEC Register of 23 Oct 2026, connecting at South Anglia Connection Node E 400kV Substation (NGET). Status: Scoping. Gate 1.
- Customer
- NOVENTUM POWER SOLAR 16 LIMITED
- Connection site
- South Anglia Connection Node E 400kV Substation
- Transmission owner
- NGET
- Technology
- Demand, Storage, Reactive Compensation
- Capacity (TEC)
- 400 MW
- Agreement
- Direct Connection
- Gate
- Gate 1
- Status
- Scoping
- MW effective from
- 31 Oct 2034
- NESO project number
- PRO-004822
Also at South Anglia Connection Node E 400kV Substation
| Project | Technology | MW |
|---|---|---|
| Lime Tree Energy Park | Storage, Solar | 249.9 |
| PVDP Woodbridge | Storage, Solar | 610 |
| Red House Farm - Friston 400kV 249MW connection | Storage | 249 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.