WindyHill BESS2 Facility
WindyHill BESS2 Facility is a storage project of 200 MW in NESO's TEC Register of 23 Oct 2026, connecting at Windyhill 275/132kV (SPT). Status: Scoping. Gate 1.
- Customer
- Windyhill Grid 2 Ltd
- Connection site
- Windyhill 275/132kV
- Transmission owner
- SPT
- Technology
- Storage
- Capacity (TEC)
- 200 MW
- Agreement
- Direct Connection
- Gate
- Gate 1
- Status
- Scoping
- MW effective from
- 27 Jul 2025
- NESO project number
- PRO-002032
Also at Windyhill 275/132kV
| Project | Technology | MW |
|---|---|---|
| WindyHill Energy Storage Facility | Storage | 200 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.